Mankhurd is a major transfer point between Mumbai’s eastern suburbs and the road to Navi Mumbai. The Ghatkopar–Mankhurd Link Road (GMLR) connects the Eastern Express Highway side of the city with the Sion–Panvel Highway near Mankhurd, carrying daily commuters as well as longer journeys toward Vashi and Pune. Its 2.9-km elevated road, opened in 2021, allows drivers to avoid several busy signals on the earlier surface route.
There is an important 2026 distinction. The existing GMLR flyover is not the same as the new Mankhurd T-junction flyover arms being built where GMLR meets Sion–Panvel Highway. Those additional arms are designed to remove the final signal and difficult turning movements toward Vashi and Ghatkopar. An October 2026 report put their work at about 40% completion, with a January 2028 target. Until those links open, drivers should expect construction-related changes at the junction rather than assuming a continuous new flyover is already available.

Mankhurd Flyover Quick Overview
| Particular | Details |
|---|---|
| Location | Mankhurd, eastern Mumbai, Maharashtra |
| Existing Main Structure | Ghatkopar–Mankhurd Link Road (GMLR) flyover |
| Existing Flyover Length | Approximately 2.9 km |
| Opened | 2021 |
| Key Connection | Ghatkopar / Eastern Express Highway side to Mankhurd |
| Major Junction | Sion–Panvel Highway T-junction near Mankhurd |
| Beyond Mankhurd | Vashi, Navi Mumbai and Pune-bound road network |
| New Project | Two additional flyover arms at the T-junction, under construction in 2026 |
| 2026 Construction Update | Reported about 40% complete in October; completion targeted for 2028 |
| Local Transport | Mankhurd railway station (Harbour Line), BEST buses, taxis and autos |
Where Is Mankhurd Flyover Located?
The existing flyover follows the Ghatkopar–Mankhurd Link Road on Mumbai’s eastern side, linking the Ghatkopar/Eastern Express Highway corridor with the Mankhurd end of the Sion–Panvel Highway. The eastern approach lies near Maharashtra Nagar and the junction where road traffic divides toward Vashi or back into Mumbai.
Do not confuse the 2.9-km GMLR flyover with the two new elevated arms at Mankhurd T-junction. Both belong to the same road corridor, but one is an operational through route and the other is an unfinished interchange intended to improve the critical turn onto the Sion–Panvel Highway.
Connectivity of Mankhurd Flyover
West of Mankhurd, GMLR is an important way to reach the Eastern Express Highway and Ghatkopar from the Sion–Panvel Highway corridor. East of the junction, Sion–Panvel Highway carries vehicles across the Vashi connection toward Navi Mumbai and the Pune route. For drivers heading in either direction, the 2021 flyover avoids a number of street-level conflicts, but it cannot by itself remove the traffic signal and merging problems at the highway T-junction.
The junction also serves residents and businesses around Mankhurd, Deonar, Govandi and Cheetah Camp. Local vehicles, buses and traffic entering service roads must share parts of the road network with faster-moving through traffic. This is why a journey can be quick on the existing elevated section but slow considerably on the approach to the Sion–Panvel Highway.
The new two-arm project is planned to separate GMLR-to-Vashi and Vashi-to-GMLR movements from the signal below. Construction in 2026 narrowed parts of the road and required traffic police to consider revised arrangements. The interchange is expected to improve conditions when finished, but its benefits should not be stated as already realised.
Directions to Mankhurd Flyover
The principal decision is whether you are using the open GMLR elevated road or approaching the still-developing T-junction at the Sion–Panvel Highway.
| Starting Point | Route / Direction |
|---|---|
| Ghatkopar / Eastern Express Highway | Follow the Ghatkopar–Mankhurd Link Road toward Mankhurd and use the operational flyover where signed. At the eastern end follow the current route for the Sion–Panvel Highway. |
| Vashi / Navi Mumbai | Head toward Mumbai over the Vashi highway connection and select the signed Mankhurd/GMLR approach. Watch for work zones before the T-junction. |
| Pune / Panvel Direction | Use the Sion–Panvel Highway toward Vashi/Mumbai. At Mankhurd choose the permitted GMLR connection for Ghatkopar; do not enter incomplete ramps. |
| Chembur / Sion Side | Travel east on the Sion–Panvel Highway to the Mankhurd junction, then follow signs for GMLR and Ghatkopar or continue toward Vashi. |
| Govandi / Deonar | Join GMLR using the designated surface-road access. Remain on local roads if the destination is a shop, housing area or stop immediately near Mankhurd. |
| Mankhurd Station / Maharashtra Nagar | Use local roads to reach the station or neighbourhood. The elevated highway is not a direct entrance to the railway station or nearby residential streets. |
Road space has been narrowed around the Mankhurd T-junction during construction. Follow current Mumbai Traffic Police diversions rather than assuming that the new arms shown on a project drawing or digital map are open.
Nearby Areas Around Mankhurd Flyover
The main flyover links suburban roads with a regional highway, while nearby areas generate local traffic at its ends.
| Nearby Area / Landmark | Why It Is Relevant |
|---|---|
| Mankhurd | Eastern Mumbai suburb and junction at the Navi Mumbai-bound highway approach. |
| Ghatkopar | Major eastern-suburbs destination on the other end of the GMLR corridor. |
| Eastern Express Highway | North–south arterial road reached through Ghatkopar-side connections. |
| Sion–Panvel Highway | Primary road from Mumbai toward Vashi, Navi Mumbai and Pune. |
| Vashi | First major Navi Mumbai centre on the eastern highway direction. |
| Govandi / Deonar | Neighbouring eastern-suburbs areas served by local GMLR roads. |
| Maharashtra Nagar | Landmark locality near the T-junction construction zone. |
| Cheetah Camp | Mankhurd-side neighbourhood whose local movements interact with the highway network. |
Public Transport and Local Access
Mankhurd station on Mumbai’s Harbour Line is a major public-transport option for the neighbourhood, although it does not have a direct entrance from the elevated GMLR carriageway. BEST buses, taxis and autorickshaws provide street-level access to Mankhurd, Govandi, Deonar and surrounding residential areas. Passengers should arrange pickups away from the highway ramps and active construction space.
The flyover itself is designed for road vehicles, not railway or Metro passengers. People travelling by train may find it simpler to reach Mankhurd or another Harbour Line station and finish the trip by local transport, depending on the final destination. Check the surface-road side of the station before booking an app cab.
Driving Tips
On this route, the biggest practical issue is the transition from a relatively free-flowing flyover to a busy highway junction and construction area.
- Distinguish the operational 2021 GMLR flyover from the under-construction T-junction arms; unfinished sections are not usable shortcuts.
- Prepare to slow near the eastern end, where GMLR traffic must merge or turn toward Sion–Panvel Highway.
- Check roadwork and lane-closure notices before commuting to Navi Mumbai, especially during peak hours.
- Leave extra distance near construction barriers, heavy machinery and narrowed carriageways; trucks and buses may need more room to turn.
- Use local service-road access for Maharashtra Nagar, Cheetah Camp and station-bound trips, rather than overshooting on the flyover.
- Reduce speed and avoid sudden braking in rain; the GMLR flyover drew attention after wet-weather skidding incidents in 2021.
- Do not stop on the elevated road for photographs, navigation or passenger pickups. Use signed exits and legal stopping places.
FAQs
Q. Are the new Mankhurd T-junction flyover arms open in October 2026?
No. The new arms were still under construction. An October 2026 report described approximately 40% progress and a January 2028 target, which is separate from the existing GMLR flyover.
Q. Why is the junction slow even after the GMLR flyover opened?
The original flyover avoids several signals along the link road, but vehicles still meet the Sion–Panvel Highway at a busy T-junction. The new interchange is specifically designed to remove some of those remaining conflicts.
Q. Does the existing flyover go all the way to Vashi?
No. The existing flyover is on GMLR and connects toward the Mankhurd junction. Vashi lies farther along the Sion–Panvel Highway corridor, beyond the junction.
Q. Will both new flyover arms serve the same traffic direction?
No. One is intended for GMLR-to-Vashi traffic, while the other is designed to bring Vashi-side traffic toward GMLR and Ghatkopar. The separation should reduce conflicting turns at the signal.
Q. Can motorists use the Mankhurd station approach as an alternative to a blocked highway lane?
Only where local traffic rules and signs permit it. Station-area streets are not designed to replace a highway interchange and can create congestion for buses, pedestrians and residents.
Q. Why do published opening targets differ for the new project?
Infrastructure schedules have changed across project reports. The safer approach is to cite a dated update rather than promise a fixed opening; the more recent October 2026 report targeted January 2028.